1 Quarterly monitoring report LWE sites Download (0.2mb) download
2 Quarterly monitoring report BharatNet Download (0.4mb) download
3 Quarterly monitoring report USOF schemes Download here (0.1mb) download
4 Quarterly summary inspection LWE Download here (0.3mb) download

 

Appendix-A

QUARTERLY MONITORING REPORT OF LWE PROJECT

Name of the Circle: A.P. Circle

Quarterly Period Ending as on: 30.06.2023

Sl No.

Quarter upto which subsidy has been disbursed

Total amount of CENVAT excess payment

Total amount of CENVAT recovered/adjusted

Total amount of Penalty imposed as per agreement

Total amount of penalty recovered/adjusted

Total no of sites commissioned

No of sites mandated for physical verification

No of sites physically verified

Shortfall/excess

Remarks

(1)

(2)

(3)

(4)

(5)

(6)

(7)

(8)

(9)

(10)

(11)

1.

MAR 2023

62873353

62873353

3485455

3485455

61

61

61

0

*

 

* Rs.  50 lakhs, Rs. 40 lakhs, Rs. 64 lakhs, Rs. 80 lakhs and Rs. 15,82,269/- (Total Rs. 2,49,82,269/-) already adjusted from the opex subsidy  claims for the Q.E. 31.12.2018, 31.03.2019, 30.06.2019, 30.09.2019 & 31.12.2019 respectively

           

 

 

Appendix-B

 

QUARTERLY MONITORING REPORT OF BHARATNET PROJECT PHASE I&II

Name of the Circle: A.P. CIRCLE

           

Quarterly Period ending as on: 30.06.2023

           

Sl No.

No. of Blocks

No of blocks commissioned

No of blocks physically inspected

No of GPs

No of GPs commissioned

No of GPs physically inspected

Percentage (Blocks+GPs)

Remarks if any

(1)

(2)

(3)

(4)

(5)

(6)

(7)

(8)

(9)

1

82

82

16

1692

1692

127

8.45%

 

                 

Note: Total Blocks(82) +GPs(1610)=1692

           

 

             

Appendix-C

QUERTERLY MONITORING REPORT OF USOF SCHEMES (OTHER THAN BHARATNET/LWE PROJECTS)

Name of the circle: Andhra Pradesh Circle

   

Quarterly period ending as on:30.06.2023

Sl No.

Name of Scheme

Quarter  upto which subsidy has been disbursed

Total no of  sites commissioned

no of sites mandated for physical verification

no of sites physically verified

Short fall/excess

Remarks

1

LWE

31.03.2022

61

100% i.e. 61

61

0

 

2

Public Rural Wi-Fi Hotspot (25000)

31.12.2022

1492

Minimum 5%.i.e. 75 Nos

101

Excess 26 Nos

Scheme completed

3

Wi-Fi Hotspot(200 Rural Railway Station)

Nil

25

Minimum 5%.i.e. 1 Nos

25

Excess 24 Nos

Mentioned below at note-1

4

O&M, FLM & provisioning of Wi-Fi Aps (under Bharatnet Phase-I)

31.12.2022

1692

Minimum 5% i.e.85 Nos

144

Excess 59 Nos

 

5

4 G based mobile services in identififed uncovered villages in aspirational districts

31.12.2022

58

 

 

 

Physical inspection to be carried out by TPA

Note-1

An amount of Rs. 1,60,62,071/- released towards mobilization advance of CAPEX i.e Rs. 89,23,373/-(50% of CAPEX)in 1st installment  on 05.02.2018 and  Rs. 71,38,698/- (40% of CAPEX) in 2nd installment  on 29.10.2018